Rapid progress at Insuratei: solar park takes shape as installation accelerates

  • Writer: cartonwies
    cartonwies
  • Jun 10, 2025
  • 1 min read

Updated: Jun 11, 2025

Construction is advancing at full speed at Alpilight’s 5.5 MWp Insuratei Solar Park, with multiple rows of solar panels now installed - bringing us closer to delivering clean energy to Romania’s grid by Q3 2025.



Structural work: 100% complete

Panel installation: Over 40% finished


Next milestones:

  • Inverter and transformer setup (June 2025)

  • Grid-connection tests (Q3 2025)

  • Battery storage integration (2026)

 
 
 